How to Review Shop Drawings Before Fabrication
A shop drawing is the document a fabricator or installer builds from. It turns the design intent into dimensions, materials, connections and quantities for one specific element, such as a steel connection, a rebar schedule, a duct run or a joinery unit. Because the workshop or the site follows it literally, a mistake that is missed at review becomes a mistake in the product. This checklist sets out what to look at, in what order, before you approve a set of shop drawings for fabrication.
By Fayez 6 min read
What are shop drawings, and who reviews them?
Shop drawings are prepared by the contractor, fabricator or a drafting team working for them. They are then reviewed by the party responsible for the design, usually the architect or engineer, and often by the main contractor first. The review does not make the reviewer the author. Its purpose is to confirm that the drawing matches the design documents and the specification, and that the product can be coordinated with the work around it.
Agree before the first submission who reviews what. A structural engineer should check structural sizes and connections, an architect should check finishes and dimensions that affect the layout, and a services engineer should check equipment and routes. Sending every drawing to one person tends to produce slow or shallow reviews.
What should you check before you start the review?
Start with the package, not the drawing content. A review that begins on the wrong revision wastes everyone's time.
- Revision and status. Confirm that the shop drawing is based on the current issue of the design drawings and that its own revision is clearly marked.
- Completeness. Check that every drawing listed in the transmittal is present, together with the calculations, product data and samples the specification calls for.
- Title block. Project name, drawing number, element reference, scale, date, author and checker should all be filled in.
- Scope. Make sure the drawings cover the whole package and that nothing has been left to be assumed.
- Standards. Check which codes, specifications and project standards apply, and that the drawing refers to the right ones.
How do you check dimensions and geometry?
Dimensional errors are the most common reason a fabricated part does not fit. Check them against the design drawings and the surrounding work rather than against the shop drawing alone.
- Compare overall dimensions, levels and grid references with the architectural and structural drawings.
- Add up the chains of dimensions. Partial dimensions should sum to the overall dimension.
- Check that the stated tolerances are achievable and consistent with the specification.
- Confirm the position and size of openings, sleeves, cast-in items and fixings.
- Look at sections and details, not only at plans. Many conflicts only appear in section.
- Check whether the drawing is based on design dimensions or on site-measured dimensions, and that this is stated.
Where a drawing relies on field measurements, ask when they were taken. If the site has changed since, the dimension may no longer be valid.
How do you check materials, finishes and connections?
Compare each stated material and grade with the specification. A substitution that looks harmless, such as a different steel grade, coating or fixing type, can change performance, so it should be raised as a formal change rather than accepted quietly.
- Materials, grades, thicknesses and section sizes match the specification and the engineer's design.
- Coatings, finishes and colours are named and match the approved samples.
- Connections, welds, bolts and fixings are shown with size, type and spacing, and are consistent with the design loads where those apply.
- For reinforced concrete, bar diameters, spacing, cover, laps and bending shapes are clear and match the structural drawings.
- Fabrication notes, such as weld symbols, surface preparation and inspection requirements, are complete.
- Quantities and schedules agree with the drawings they refer to.
The responsible engineer should confirm structural connections and reinforcement. A drafter or coordinator can check that the drawing is complete and consistent, but cannot replace that engineering approval.
How do you check coordination with other trades?
A shop drawing can be correct on its own and still clash with the work around it. Coordination checks are where a model-based workflow helps, because the elements can be compared in one space. Our guide to BIM level of development explains how much detail a model carries at each stage, and what a Revit model should contain lists the content by discipline.
- Check ducts, pipes, cable trays and structure in the same area for physical clashes and for access and maintenance space.
- Check that openings and sleeves for services are shown on the structural drawings and match the services drawings.
- Check supports and hangers against the structure they will be fixed to.
- Check that finishes, ceilings and fire-rated elements are compatible with what passes through them.
- Look at installation sequence. Some items cannot be fitted once the neighbouring work is in place.
How should you record the review?
Use a consistent set of review outcomes and apply them in the same way each time. The names vary between contracts, but they usually mean approved, approved with comments, revise and resubmit, or rejected. Write comments so they can be acted on: say what is wrong, where it is, and what is expected instead.
- Mark up the drawing itself and number each comment, so the response can refer to it.
- Keep comments to the drawing under review. New design requests belong in a separate instruction.
- Require a written response to every comment on resubmission, with a revision cloud or note on the changed area.
- Keep a register of submissions, revisions and outcomes. It shows what was approved and when.
- Do not release fabrication until the status allows it.
First-pass approval is a useful measure of drawing quality, because a drawing that is returned costs time in the design office and on site. For an example of a large shop-drawing package reviewed by a main contractor, see the King Salman Park case study.
What helps the shop drawing team get it right first time?
Most returned drawings trace back to the brief. Give the drafting team the design drawings at the current revision, the specification sections that apply, the project templates and layer or naming standards, the review contacts for each discipline, and the submission procedure. Our guide on how to brief a CAD drafter lists what to send, and the CAD file formats guide explains which formats to exchange.
OEG's CAD and BIM teams work in your templates and standards, in Revit, AutoCAD and Navisworks, from LOD 100 to 500. See our BIM modelling and coordination services and the dedicated CAD and BIM team, or book a consultation to discuss your project.
If the drawings are prepared by an offshore team, working with an offshore drafting team explains how to set up handover and review cycles.
For how conflicts between disciplines are found in a model, see BIM coordination and clash detection explained.
Frequently asked questions
How long should a shop drawing review take?
The contract usually sets a review period. Within it, the time depends on the size and complexity of the package, so agree the sequence and priorities with the drafting team in advance.
Who is responsible if an approved shop drawing contains an error?
This depends on the contract. In many contracts, approval does not remove the fabricator's responsibility for dimensions and coordination. Check the wording of your contract with your adviser.
What is the difference between shop drawings and design drawings?
Design drawings show what is to be built. Shop drawings show how a specific element will be made and installed, with the detail a workshop or installer needs.
Can shop drawings be produced from a BIM model?
Yes. Many shop drawings are generated from a coordinated model and then annotated, dimensioned and checked. They still need the same review before fabrication.