As-Built Drawings from Site Surveys: A Practical Guide
As-built drawings record a building as it actually stands, not as it was designed. They matter when you renovate, extend, manage or sell a property, and when the original drawings are missing or no longer match the site. Producing them well starts on site, with a survey that captures the right information, and ends in the office, with a drawing that others can rely on. This guide explains how the process works and how to get a reliable result.
By Fayez 5 min read
What are as-built drawings?
The term is used in two ways. On a construction project, as-built or record drawings are the contractor's updated drawings showing changes made during construction. For an existing building with no reliable records, as-built drawings are new drawings prepared from a survey of the building as found. This guide is mainly about the second case, although the same drafting steps apply to both.
Typical outputs are floor plans, sections, elevations, roof plans and sometimes a site plan. They can be 2D CAD drawings or a 3D model. If you are choosing between the two, read 2D CAD drafting vs 3D BIM modeling.
How do you collect the survey data?
The method depends on the size of the building, the accuracy needed and the budget. The common ones are:
- Tape and laser measurement. Hand measurement with tape, or a handheld laser distance meter, plus sketches and photographs. Suitable for small buildings and simple layouts.
- Total station. A surveying instrument that records precise points. Useful for façades, levels and controlled coordinates.
- 3D laser scanning. A scanner records millions of points to produce a point cloud. Suitable for complex or large buildings, and for any case where completeness matters.
- Photogrammetry. Measurements derived from overlapping photographs, often used for façades and roofs.
Each method has limits. A laser scan sees only surfaces it can reach, so voids above ceilings, inside walls and below floors are not captured. Plan for inspection openings if concealed services matter.
What should the survey capture?
- Overall dimensions, wall thicknesses and the position of each wall relative to the grid or a reference line.
- Floor-to-floor and ceiling heights, and level changes within each floor.
- Doors, windows and other openings, with sizes, sill heights and head heights.
- Stairs, ramps, lifts, shafts and roof geometry.
- Structural elements that are visible: columns, beams, walls and slab edges.
- Services that are visible and relevant to the brief, such as risers, plant, panels and main routes.
- Photographs tied to locations, and notes on anything unusual or inaccessible.
Agree the scope before the visit. A drawing set for a fit-out needs different information from a structural assessment or a facade survey.
How are the drawings produced from the survey?
The drafting team turns survey data into drawings. The steps are:
- Register and check the data. Control points, measurements and scans are brought into one coordinate system. Closing errors are checked before any drawing starts.
- Set up the drawing. Use your template, units, layers and title blocks. See the guide to briefing a CAD drafter for what to provide.
- Draw the building. Walls, openings, stairs, structure and fixed items are drawn from the survey. With a point cloud, the drafter traces the cloud in CAD or builds a model from it.
- Annotate. Add dimensions, room names, levels, notes and a north point.
- Check against the source. Overlay the drawing on the survey data, or compare key dimensions with the measurements, and correct differences.
- Issue and review. Send the drawings with a list of assumptions and open questions for the client or surveyor to confirm.
For models built from scans, see scan to BIM: from point cloud to Revit model. If your starting point is old paper drawings rather than a survey, CAD conversion explains how to bring them into CAD, and why they should still be checked against the building.
How accurate will the drawings be?
Accuracy depends on the survey method, the care taken on site and the drafting. Agree a tolerance before the work, in the units you use, and state it on the drawings. Tape surveys are generally less precise than scans or total station surveys, and old buildings are rarely square or plumb, so drawing a clean orthogonal plan means deciding what to straighten and what to show as found. Record that decision in the notes.
The drawing is also only as current as the survey date. Alterations after the visit will not appear, so date every issue.
How do you check as-built drawings?
- Measure a set of dimensions on site that were not used to produce the drawing, and compare them.
- Check that plans, sections and elevations agree with each other.
- Check that floor levels and heights are consistent across the building.
- Check that openings in the drawing match photographs.
- Check that areas, if stated, are calculated by an agreed rule.
- Read the notes and assumptions. Anything the surveyor could not access should be listed as unverified.
What should you send to a drafting team?
Send the raw survey data, not only a summary: sketches with dimensions, photographs, point cloud files or total station output, any old drawings, and a note of the survey date and method. Add your template, the formats you need back, the scope and the tolerance. For file questions, read CAD file formats: DWG, DXF, RVT and IFC. For the types of drawings and what the service covers, see CAD drafting services: what they include and how to choose, and architectural drafting outsourcing for what to expect back.
OEG's team drafts in AutoCAD and Revit, in your templates and standards. See the BIM modelling and coordination services and the dedicated CAD and BIM team, or book a consultation to discuss a survey package.
Frequently asked questions
Can as-built drawings be made from photographs alone?
Photographs help with details, but dimensions need measurement. Use photographs to support a survey, not to replace one.
Do I need a point cloud?
Not always. A tape survey can be enough for a small building with simple geometry. A scan is worth considering when the building is large or complex, or when you need a full record.
Why do as-built drawings differ from the original design drawings?
Changes are made during construction and after it, and many are never recorded. The survey shows what is actually there.
Who is responsible for the accuracy of the survey?
This depends on who carried it out and on your agreement. If the drafting team did not do the survey, they are responsible for drawing accurately from the data they were given.